Nortel Networks BCM200/400 Telephone User Manual


 
262 Chapter 12 Install Companion or DECT Systems
P0993133 03
Attach a Companion Base Station to a wall or ceiling
Install base stations on a wall or on a ceiling. When installing base stations on a wall, install them
with their covers at the bottom, as shown in Figure 169 on page 263. Allow for clearances around
the base station as indicated in Table 32.
Use this procedure to install a base station:
1 Fasten the bracket into position using two #8 38-mm (1-1/2 in.) screws.
2 Route the cable from the Business Communications Manager system through the top or
bottom opening.
3 Wind any excess cable around the posts, then fasten the cable under the strain relief.
4 Connect the wires to the BIX connector on the bracket termination board as shown in Figure
168.
Figure 168 Bracket termination board
Table 31 Minimum distance between office areas and base stations
Number of base stations in the cell Minimum distance between office areas and base stations
1 1 m (40 in.)
2 1.4 m (56 in.)
3 1.8 m (72 in.)
4 2 m (80 in.)
Table 32 Clearance for the base stations
Clearance conditions Canada USA
Clearance from all other objects 9 cm 3.5 in.
Vertical clearance from base station center to base station center 27 cm 54 in.
Horizontal clearance from base station center to base station center 41 cm 54 in.
-PWR(1)
TCM
+PWR(1)
+PWR(2)
-PWR(2)
TCM
RJ11 jack
TCM
RJ11 jack
TCM
-PWR(2)
+PWR(1)
+PWR(2)
-PWR(1)