Page 354 of 466 Installing the Main Distribution Frame
NN43041-310 Standard 01.11 October 2008
Procedure 81 describes how to install the Krone Test Jack Frame for the UK.
For detailed information, refer to the Krone documentation.
Procedure 81
Installing the Krone Test Jack Frame (UK)
1 Refer to the equipment layout plan to determine where to place the
cross-connect terminal.
2 Lay out the terminal blocks as shown in Figure 152 on page 355.
3 Attach labels on the cross-connect terminal to indicate the terminal blocks
assigned to the following:
• Analog Line cards
• DC15/AC15/RAN/PAG cards
• Data Access cards
•AUX wiring
• Power Fail Transfer Units
• Digital Line cards
• Telephones
• Exchange Line Trunk cards
• Direct Dialing Inward trunk cards
• Miscellaneous equipment