Nortel Networks 1000E Telephone User Manual


 
Installing software on the CS 1000E Page 139 of 466
Communication Server 1000E Installation and Commissioning
Complete the CP PM installation
Testing the CP PM Call Servers
Procedure 24
Testing CP PM Call Server 0
At this point in the installation, CP PM Call Server 0 is tested from active CP
PM Call Server 1. Upon successful completion of these tests, call processing
is switched and the same tests are performed on CP PM Call Server 1 from
active CP PM Call Server 0. As a final step, call processing is then switched
again to CP PM Call Server 1.
From active CP PM Call Server 1, perform the following tests on CP PM
Call Server 0:
1 Perform a redundancy sanity test:
2 Check the LCD states
a. Perform a visual check of the LCDs.
b. Test and LCDs:
c. Check that the LCD display matches the software check.
3 Test the System Utility card
LD 135
STAT CPU Get status of CPU and memory
TEST CPU Test the CPU
LD 135
TEST LEDs Test LEDs
DSPL ALL
LD 135 Load program
STAT SUTL Get the status of the System Utility card
TEST SUTL Test the System Utility card