Nortel Networks 1000E Telephone User Manual


 
Installing software on the CS 1000E Page 147 of 466
Communication Server 1000E Installation and Commissioning
TLAN set to auto negotiate.
ELAN set to auto negotiate.
ELAN security Enabled, level is Optimized Security
Is this correct? (y/n/[a]bort) : y
4 IP changes require a reboot. Enter “y” at the prompt.
Do you want to continue? (y/n/[a]bort) : y
reboot(-1) has been called...
Following the reboot, the MGC connects to the CS and downloads the
remaining configuration information.
If centralized software upgrade has been enabled, the MGC will upgrade its
loadware by downloading it from the CS.
Once the MGC has registered, the LED display will show the superloop and
shelf (for example: 4 0) of the IPMG. Otherwise, it will show “UNRG.”
Configuring the IPMG zone and IP address
The next step in the process involves configuring the IPMG zone and IP
address in Overlay 97 on the Call Server.
Note: This procedure may be performed through Element Manager
following the installation of the Signaling Server. To configure an IPMG
using Element Manager see Procedure 48 on page 240.
1 Log into Overlay 97 to configure the MGC that will register to the call
server:
>LD 97
SCSYS000
MEM AVAIL: (U/P): 103979814 USED U P: 230475 59531
TOT: 104269820
REQ prt
TYPE supl
SUPL
SUPL SUPT SLOT XPEC0 XPEC1 IPMG ZONE0/1 IPR0/1