NEC NEAX 2000 IVS2 IP Phone User Manual


 
CHAPTER 4 CIRCUIT CARD INFORMATION
PN-DAIA (DAI)
NEAX2000 IVS
2
Remote PIM System Manual
ND-70917 (E), Issue 1.0
Page 75
NOTE 3: When the source clock signal is supplied via the line between the Main Site and the
Remote Site, set the SW1-1 and SW1-2 as indicated in the following table. In this case,
DAIA cards (DAIA0, DAIA1) must be mounted in PIM0.
NOTE 4: Time Slot Number 0, 20, 21, and 22 (TS0/20/21/22) cannot be used for control signal.
NOTE 5: This setting must be identical with the opposite DAIB card.
CONDITIONS
DAIA0 DAIA1 DAIA2
REMARKS
SW
1-1
SW
1-2
SW
1-1
SW
1-2
SW
1-1
SW
1-2
One DAIA card
is provided.
ON OFF Clock signal is sent to
PLO0 of MP card via
Supply Route 0
(DAIA0).
Two or three
DAIA cards are
provided.
ON OFF OFF ON OFF OFF Clock signal supply
route automatically
changes to Route 1
(DAIA1), if a
transmission line
failure occurs on
Supply Route 0.