SpectraLink Link 150 M3 MCU Cordless Telephone User Manual


 
SpectraLink Corporation Installation and Operation
Link WTS – Link 150 M3 MCU
2.1 Installation Steps and Responsibilities
9
Task
Description
Wire
Contractor or
Electrician
Field
Service
Engineer
Customer
Project Mgr/
System Admin
Site Preparation
Determine location of MCU
9
Run Cable for System
Run cable to Base Station locations
9
Pull cable
9
Terminate cable at Base Station locations
9
Prepare and install demarc blocks
9
Assign and program ports
9
Connect cables to demarc blocks
9
Install SpectraLink System
Survey site and check components
9
Install MCUs
9
Install Base Stations
9
Install outdoor Base Stations
9
Connect and register handsets
9
Set up diagnostic modem
9
Register handsets
9
Program handset features
9
Test handsets
9
Site certification
9
PN: 72-0075-01-F.doc Page 8