NEC 120 Answering Machine User Manual


 
AD-25182501 CHAPTER 3
Page 17
Revision 1.0.1
NAP- 200-002
Sheet 1/2
Marking and Drilling
1. Confirmation of the Equipment Layout
Install the equipment in an area which provides adequate ventilation and is easily accessible to service personnel.
2. Marking and Drilling
2.1 Floor Standing
By referring to Figure 002-1, mark and drill the installation holes for the main equipment.
Mark and drill the installation holes for the external BATTM and MDFM, if required.
Refer to Figure 003-1 for details.
Figure 002-1 Floor Marking for Main Equipment
39
110
35
37
356
430
37
WALL
RACK PARTS
40
184
FRONT
UNIT: mm